Roof installationIn progress

Industrial hall re-roofing

Slovakia2026

Strip and replacement of an existing flat roof with a membrane waterproofing system on a manufacturing facility.

Industrial hall re-roofingRoof installation

Overview

A re-roofing of a manufacturing hall, replacing a worn flat roof with a new membrane waterproofing system over the working facility. The project is currently underway.

The brief

The hall stays in production during the works, so the roof has to be stripped and re-covered in sections that are made watertight each day without interrupting the operation below.

What we did

Survey and build-up specification
Phased strip-out of the existing flat roof
New insulation and membrane waterproofing
Renewed flashings, upstands and outlets
Roof drainage

How we did it

01

Survey & plan

We surveyed the existing roof and planned a phased build-up that keeps the hall watertight day to day.

02

Phased strip-out

The worn covering is being removed in sections sized to be re-covered within each working window.

03

New waterproofing

Insulation and a new membrane system are being laid, with flashings and outlets renewed.

04

Drainage & completion

Roof drainage is being brought up to standard as each section is closed in.

Where it stands

Work is progressing section by section, keeping the facility in production while the roof is replaced; completion and handover are scheduled within the current programme.

Trade
Roof installation
Location
Slovakia
Year
2026
Status
In progress